Your company is interested in having a new facility constructed. The contractor expects that it will take approximately 3 years to complete the building. The contractor has offered you three payment plans for the building. They are as follows:

Time

Plan 1

Plan 2

Plan 3

Today

$7,200,000

$10,800,000

$0

1 year from now

$23,400,000

$0

$39,150,000

2 years from now

$23,400,000

$34,200,000

$0

3 years from now

$23,400,000

$34,200,000

$39,150,000

The CFO of your company has asked you to provide recommendation concerning which payment plan to accept. What is your recommendation? Assume your weighted-average cost of capital is 14%.