The beta project team has started gathering the information


Project Management Exercise -

The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The results of their meeting are found in the following table.

Activity

Description

Duration

Predecessor

1

Define Scope

6

None

2

Define Customer Problems

3

1

3

Define data records and relationship

5

1

4

Mass Storage Requirements

5

2, 3

5

Consultant Needs Analysis

11

2, 3

6

Prepare Installation Network

3

4

7

Estimate Costs and Budgets

2

4

8

Design Section Point System

1

4, 5

9

Write Request Proposal

5

5

10

Compile Vendor List

2

5

11

Prepare MGMT Control System

5

6, 7

12

Prepare Comparison Report

5

9, 10

13

Compare System Philosophies

5

8, 12

14

Compare Total Installation

2

8, 12

15

Compare Cost of Support

3

12

16

Compare Customer Satisfaction Level

8

12

17

Assign Philosophies Points

1

13

18

Assign Installation Cost

1

14

19

Assign Support Cost

1

15

20

Assign Customer Satisfaction Points

1

16

21

Select Best System

2

11, 17, 18, 19, 20

22

Order System

1

21

The project team has requested that you create a network diagram for the project, identify the critical path, and determine if the project can be completed in 50 weeks.

You are to first do a "hand drawn" solution, and then use Microsoft Project to create network diagram again. Assumptions: Start date is October 3, 2016, one shift per day, no overtime, no weekends, and all traditional holidays to be observed.

Request for Solution File

Ask an Expert for Answer!!
Project Management: The beta project team has started gathering the information
Reference No:- TGS01621722

Expected delivery within 24 Hours