The best case scenario has an npv of 20000 and probability


There are three scenarios for a project. The Best Case scenario has an NPV of $20,000 and probability of 30%. The Base Case scenario has an NPV of $1,000 and probability of 45%. The Worst Case scenario has an NPV of ($5,000) and a probability of 25%. (show work

a) What is the expected NPV of the project?

b) What is the variance of the project?

c) What is the standard deviation of the project?

d) What is the Coefficient of Variation of the project?

Solution Preview :

Prepared by a verified Expert
Finance Basics: The best case scenario has an npv of 20000 and probability
Reference No:- TGS02773019

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)