The arts center has an annual season preview where patrons


The Art's Center has an annual season preview where patrons are able to purchase tickets early. There are six stations. An average of 63 patrons arrive per hour. Each station spends an average of 16 minutes with each order. However The Gallo Center does not want their donors to wait longer than an average of 16 minutes. Should they add a 7th station to alleviate the problem? show work please.