The arc company specializes in developing and selling a


The ARC Company specializes in developing and selling a wide range of highquality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these type of razor scooters will be featured in the XGames. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

Part A: Enter the tasks You are a member of a project team assigned to develop the new razor scooter code named “Blue Zuma”. The table A.1 contains the information necessary to create a project schedule. For the purposes of this case assume the following:

• Time Durations are in Days

• The project begins January 1, 2016. •

Assume that no work is completed on weekends

Table A.1 2. Create a Memo that answers the following questions:

1. What is the project duration based on Te?

2. What is the critical path for this project? (use ID numbers such as 2-->3-->5, etc.)

3. How many tasks are on the critical path?

4. What is the chance that the project will be completed in the duration of our current critical path?

5. What time should the project manager estimate if he or she wants to be 95% sure that the project will be completed within that time period?

6. What is the buffer time that should be added to a project’s critical tasks in order to be 95% sure that the project completes on time.

ID Description a m p Predecessor

1 Blue Zuma Product (Summary Task)

2 Market Analysis 20 25 30

3 Product Design 38 40 45 2

4 Manufacturing Study 15 20 25 2

5 Product Design Selection 9 10 12 3, 4

6 Detailed Marketing Plan 12 15 18 5

7 Manufacturing Process 25 30 40 5

8 Detailed Product Design 35 50 55 5

9 Test Prototype 10 10 15 8

10 Finalized Product Design 20 25 30 7, 9

11 Order Components 5 7 8 10

12 Order Production Equipment 10 14 15 10

13 Install Production Equipment 30 35 40 11FS+20d, 12FS + 40d

14 Celebrate 1 1 1 6, 13