The amount of gross profit


In 2013 Tarlo Company agrees to construct a highway for Brice County over a three-year period. The contract price is $1,200,000 and the construction costs total $705,000 for the three years. The percentage completed at the end of each year is as follows: 2013, 20%; 2014, 75%; 2015, 100%.
Required
1. Prepare a schedule showing the amount of gross profit that Tarlo Company recognizes each year using the percentage-of completion method.
2. Prepare a schedule showing the amount of gross profit that Tarlo Company recognizes each year using the completed contract method.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: The amount of gross profit
Reference No:- TGS0677301

Expected delivery within 24 Hours