The air pollution project discussed in the chapter has


The air pollution project discussed in the chapter has progressed over the past several weeks, and it is now the end of week 8. Lester Harky would like to know the value  of the work completed and the amount of any cost overruns or underruns for the project by developing a table like Table 5 on page 7 in the notes.The revised cost figures are shown in the following table 

Activity

Total budgeted cost ($)

Percent of completion

Actual Cost

A

25800

100

30000

B

35650

100

35000

C

21300

100

24000

D

40000

80

31500

E

51800

65

34500

F

29800

40

16500

G

68470

10

8200

H

20300

2

1250

Please show all work