The action toy company has decided to manufacture a new toy


The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,600 units per 40-hour workweek. TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS A, 24, - B, 28, A C, 14, A D, 14, A E, 10, B,C F, 27, D,E C.) The total idle time per cycle for the process is?? (whole number) TASK, WORKSTATION NUMBER A, STATION 1 B, STATION 2 C, STATION 3 D, STATION 4 E, STATION 4 F, STATION 5 D.) The efficiency of the assembly line with 5 work stations equals??(one decimal place) E.) if one used 6 work stations instead of 5, the efficiency of the assembly line would be what??(one decimal place)