The action toy company has decided to manufacture a new toy


The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,600 units per 40-hour workweek.

TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS

A. 24, -

B. 28, A

C. 14, A

D. 14, A

E. 10, B,C

F. 27, D,E

C) The total idle time per cycle for the process is?? (whole number)

TASK, WORKSTATION NUMBER

A. STATION 1

B. STATION 2

C. STATION 3

D. STATION 4

E. STATION 4

F. STATION 5

D) The efficiency of the assembly line with 5 work stations equals??(one decimal place)

E) If one used 6 work stations instead of 5, the efficiency of the assembly line would be what??(one decimal place)