The acme rodenticide company has the following projected


The ACME rodenticide company has the following projected requirements for packs of its rat poison:

Week June 1:     2350

Week June 8:     2460

Week June 15:     1590

Week June 22:    2789

Week June 29:    1962

Week July 6:     1757

Before June 1, a stocktake shows that there are 3367 units in stock.

The following production rules apply:

There is a one week production lead-time

The batch size is 250 units

There is a safety stock requirement of 500units

You should product the minimum amount in any week to meet requirements and not breech the safety stock requirements

Construct an MRP record.