Texco under-or overapplied overhead


Problem: Texco Corporation uses an activity-based costing system with two activity cost pools. Texco uses direct labor hours as the measure of activity in the first activity cost pool and the number of orders in the second activity cost pool. The following information relates to these two activity cost pools for last year:

Budgeted Actual

Activity cost pool 1

Direct labor hours 120,000 145,000
manufacturing overhead cost $600,000 $580,000

Activity cost pool 2:

Number of orders 4,000 3,600
Manufacturing overhead cost 320,000 360,000

What was Texco's under- or overapplied overhead for last year?

A) $17,000 overapplied

B) $20,000 underapplied

C) $27,000 underapplied

D) $73,000 overapplied

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Texco under-or overapplied overhead
Reference No:- TGS01738496

Now Priced at $20 (50% Discount)

Recommended (94%)

Rated (4.6/5)