Tanner Manufacturing Expected Job No. 26 to cost $300,000 of overhead, $500,000 of materials, and $200,000 in labor. Tanner applied overhead based on direct labor cost. Actual production required an overhead cost of $290,000, $550,000 in materials used, and $220,000 in labor. All of the goods were completed. What amount was transferred to Finished Goods?