Suppose you calculated the mean and the standard deviation


Suppose you calculated the mean and the standard deviation of the critical path (longest path) as mean = 100 days, standard deviation as 10 days. The mean and the standard deviation of the second longest path are 95 and 12 days, respectively. Which of the following statements is true?

I. The second longest path can be longer than the critical path

II. Simulation and PERT would give very similar answers for the 90th percentile of the project duration

III. PERT bias would be insignificant (negligible) for this problem

a) I

b) II

c) III

d) II & III

e) None of them is correct

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Suppose you calculated the mean and the standard deviation
Reference No:- TGS01532752

Expected delivery within 24 Hours