Suppose that for an engineering project the optimistic most


Question: Suppose that, for an engineering project, the optimistic, most likely, and pessimistic estimates are as shown in the accompanying table. Develop a spreadsheet to determine the AW for each of the three estimate conditions. It is thought that the most critical elements are useful life and net annual cash flow. Include in your spreadsheet a table showing the AW for all combinations of the estimates for these two factors, assuming that all other factors remain at their most likely values.

                                                             Optimistic                      Most Likely                       Pessimistic

Capital                                                      $90,000                        $100,000                         $120,000
investment

Useful life                                                  12 years                         10 years                          6 years

Market value                                              $30,000                         $20,000                               $0

Net annual                                                $35,000                          $30,000                           $20,000
cash flow

MARR (per                                                   11%                                11%                                11%
year)