Suppose that after 12 days activities 1 9 and 2 have been


Suppose that after 12 days, activities 1, 9, and 2 have been finished; activity 3 is 75 percent finished; and activity 10 is half finished. How many days after the original start time would the project finish? (Written work to be placed in a Microsoft Word file and POM and Excel Files uploaded for support