Suppose that a major cityrsquos main thoroughfare which is


Suppose that a major city’s main thoroughfare, which is also an interstate highway, will be completely closed to traffic for two years, from January 2014 to December 2015, for reconstruction at a cost of $535 million. If the construction company were to keep the highway open for traffic during construction, the highway reconstruction project would take much longer and be more expensive. Suppose that construction would take four years if the highway were kept open, at a total cost of $800 million. The state department of transportation had to make its decision in 2014, one year before the start of construction (so that the first payment was one year away). So the department of transportation had the following choices: (i) Close the highway during construction, at an annual cost of $267.5 million per year for two years. (ii) Keep the highway open during construction, at annual cost of $200 million per year for four years.

Suppose the interest rate is 10%. Calculate the present value of the costs incurred under each plan.

The present value of plan (i) is: $ million. (Round your answer to two decimal places.)

The present value of plan (ii) is: $ million. (Round your answer to two decimal places.)

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Suppose that a major cityrsquos main thoroughfare which is
Reference No:- TGS01218893

Expected delivery within 24 Hours