Suppose in problem that additional constraints arise from


Question: Suppose in Problem that additional constraints arise from the fact that certain tasks cannot be performed at the same station. In particular suppose that the tasks are zoned in the following manner.

Assuming that only tasks in the same zone category can be performed at the same station, determine the resulting line balance for Problem based on a 45-second cycle time.

Problem: The assembly of a transistorized clock radio requires a total of 11 tasks. The task times and predecessor relationships are given in the following table.

1772_Task 3.png

a. Develop a network for this assembly operation.

b. What is the minimum cycle time that could be considered for this operation? What is the minimum number of stations that could be used with this cycle time?

c. Using the ranked positional weight technique, determine the resulting balance using a cycle time of 45 seconds.

d. Determine by experimentation the minimum cycle time that results in a four-station balance.

e. What is the daily production rate for this product if the company adopts the balance you determined in part (c)? (Assume a six-hour day for your calculations.) What would have to be done if the company wanted a higher rate of production?

Request for Solution File

Ask an Expert for Answer!!
Data Structure & Algorithms: Suppose in problem that additional constraints arise from
Reference No:- TGS02265108

Expected delivery within 24 Hours