Suppose a project has two possible outcomes there is a 30


Suppose a project has two possible outcomes. There is a 30% chance that it brings a profit of 10,000. There is a 70% chance that it brings a profit of 3,600. Suppose a decision makers utility function can be described by U(w)=w^0.5. What is this project's certainty equivalence for this decision maker?