Summer tyme inc is considering a new 3-year expansion


Summer Tyme, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $3.402 million. The fixed asset will be depreciated straight-line to zero over its 3-year tax life, after which time it will have a market value of $264,600. The project requires an initial investment in net working capital of $378,000. The project is estimated to generate $3,024,000 in annual sales, with costs of $1,209,600. The tax rate is 31 percent and the required return on the project is 9 percent.

What is the project's year 0 net cash flow?

What is the project's year 1 net cash flow?

What is the project's year 2 net cash flow?

What is the project's year 3 net cash flow?

What is the NPV?