Sue helms appliances wants to establish an assembly line to


Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows:

Task

Time (min)

Immediate Predecessors

A

10

-

B

12

A

C

8

A, B

D

6

B, C

E

6

C

F

6

D, E

a) What is the theoretical minimum for the smallest number of workstations that Helms can achieve in this assembly line?

b) Graph the assembly line, and assign workers to workstations. Can you assign them with the theoretical minimum?

c) What is the efficiency of your assignment?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Sue helms appliances wants to establish an assembly line to
Reference No:- TGS02155924

Expected delivery within 24 Hours