Sudler production is planning to sell 600 boxes of ceramic


Sudler Production is planning to sell 600 boxes of ceramic tile, with production estimated at 580 boxes during May. Each box of tile requires 44 pounds of clay mix and a quarter hour of direct labor. Clay mix costs $0.50 per pound and employees of the company are paid $15.00 per hour. Manufacturing overhead is applied at a rate of 110% of direct labor costs. Sudler has 2,600 pounds of clay mix in beginning inventory and wants to have 3,000 pounds in ending inventory. What is the total amount to be budgeted for manufacturing overhead for the month?

$2,475.00

$9,900.00

$2,392.50

$9,570,00

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: Sudler production is planning to sell 600 boxes of ceramic
Reference No:- TGS01070962

Expected delivery within 24 Hours