Station 3 5467 must be marked in the field if the steel


Station 3 + 54.67 must be marked in the field. if the steel tape to be used is only 99.98 under standard conditions and if the temperature is 87 degree farenheit at the time of the measurement, how far away from the existing station mark at 0 + 79.23 will the surveyor have to measure to locate the new station?.

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: Station 3 5467 must be marked in the field if the steel
Reference No:- TGS0816090