State the critical path - what is the duration of the


Use the following table to answer the succeeding questions (duration in days):

ACTIVITY

DEPENDENCY

DURATION

A

-

6

B

A

     4

C

B, E

3

D

-

5

E

A, D

2

F

-

1

G

F

7

H

C,E,G

2

I

G

4

J

C

8

1. Construct the network diagram.

2. State the critical path.

3. What is the duration of the project?

4. State in table format, the ES, LF and slack for activities E, H and I.

5. What would happen to the project if there is a delay of two (2) days in activities B and F?

Solution Preview :

Prepared by a verified Expert
Project Management: State the critical path - what is the duration of the
Reference No:- TGS01008355

Now Priced at $10 (50% Discount)

Recommended (93%)

Rated (4.5/5)