Springfield is planning to build a new water treatment


Springfield is planning to build a new water treatment facility. The first cost of the facility will be $906711. Annual maintenance and repairs will be $16867 for each of the first 5 years, increase to $46917 for each of the next 10 years, and increase again to $55931 for each of the next 5 years. Springfield is also planning for a major overhaul at the end of 10 years which is estimated to cost $215858 and another minor overhaul at the end of 17 years which is estimated to cost $25979. Using an interest rate of 2.5%, what is the equivalent uniform annual cost (EUAC) for this system?