Spending variance for supply costs problem


Brattain Tile Installation Corporation measures its activity in terms of square feet of tile installed. Last month, the budgeted level of activity was 1,230 square feet and the actual level of activity was 1,140 square feet. The company's owner budgets for supply costs, a variable cost, at $2.10 per square foot. The actual supply cost last month was $3,260. In the company's flexible budget performance report for last month, what would have been the spending variance for supply costs?

A) $866 U

B) $257 F

C) $677 U

D) $189 F

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Spending variance for supply costs problem
Reference No:- TGS078466

Expected delivery within 24 Hours