Some of the main inputs to rough-cut capacity plan rccp


Some of the main inputs to rough-cut capacity plan (RCCP) include:

a. bill of resources, bill of materials, master demand schedule, and accounting/finance.

b. bill of resources, bill of materials, material requirements plan, and accounting/finance.

c. bill of resources, bill of materials, master demand schedule, and inventory item attributes.

d. bill of resources, bill of materials, material requirements plan, and supply chain bill.

e. all of the above is true.