Problem: Solve the transportation problem below using the Northwest Corner method, the Intuitive Lowest-Cost method, and the Stepping-Stone method.

 Plants             Supply                 Destination       Demand

Kansas City         35                       Chicago           30

Omaha                50                        St. Louis          65

Des Moines          50                        Cincinnati        40

Total                  135 tons                     Total          135 tons

 

Transport cost from Plants to Destinations ($/ton)

 

Plants

Chicago

St. Louis

Cincinnati

Kansas City

Omaha

Des Moines

                $4

6

8

3

7

2

3

6

5

 