Slow ride corp is evaluating a project with the following


Slow Ride Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 29,900 1 12,100 2 14,800 3 16,700 4 13,800 5 – 10,300 The company uses an interest rate of 10 percent on all of its projects. Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) MIRR % Calculate the MIRR of the project using the reinvestment approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) MIRR % Calculate the MIRR of the project using the combination approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) MIRR %