Sleep tight inc manufactures bedding sets the budgeted


Problem

Sleep Tight, Inc. manufactures bedding sets. The budgeted production is for 52,700 comforters this year. Each comforter requires 1.5 hours to cut and sew the material. The cost of cutting and sewing labor is $12.20 per hour. Determine the direct labor budget for this year.