Skilled labor is required to produce the handles and the


Problem:

The Chop is the manufacturer of the store brand of hatchets and axes sold by various home hardware supply stores.  Each item consists of a hickory handle produced in the local processing facility and a steel blade forged and polished in the local machine shop.  These two items are then transported to an assembly area where the blade is attached to the handle and the item is packaged for shipment to destination stores. Because of its exclusive contracts with various stores, the shop can sell any amount of product it produces.

Skilled labor is required to produce the handles and the blades. Cheaper unskilled labor is used to assemble and package the final products.  There is sufficient storage area of store the finished product prior to shipping. Assume all raw material is on-hand at the start of the quarter and there is no way to obtain additional raw material or to schedule additional labor hours.

The following provides data on a per item, per product basis:

 

Hatchet

Ax

Selling price to stores

$16.00

$29.50

Hickory required (ft/unit)

1.6

3.1

Steel required (lbs/unit)

1.8

4.2

Skilled labor required per unit produced

 

 

Handle production (min/unit)

5.0

2.6

Blade production (min/unit)

11.0

9.4

Unskilled labor required per unit produced

 

 

Assembly (min/unit)

4.0

5.5

Packaging (min/unit)

2.0

2.5

 

The following data summarizes important information for the next three months (the next quarter):

 

June

July

August

Contracted requirements

 

 

 

Minimum Hatchet production

200

200

225

Minimum Ax production

200

250

300

Costs

 

 

 

Skilled labor ($ per hour)

$12.00

$12.00

$12.84

Unskilled labor ($ per hour)

$7.00

$7.00

$7.35

Hickory ($ per linear foot)

$1.00

$1.20

$1.05

Steel ($ per pound)

$1.18

$1.06

$0.98

The following table provides and summary of the resource availability over the next three months.

 

Availability

Resource

June

July

August

Skilled Labor (total hours)

220

250

200

Unskilled Labor (total hours)

120

100

140

Hickory (total linear feet)

2000

2200

1500

Steel (pounds)

2000

2000

2000

Tasking:

Management needs to know the production schedule for June, July and August that maximizes profit.  Given this production schedule, provide a 1) summary of resources used by month, by product and 2) profits by month, by product.

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Skilled labor is required to produce the handles and the
Reference No:- TGS01269402

Now Priced at $30 (50% Discount)

Recommended (90%)

Rated (4.3/5)