Sketch network to represent possible subcontractor-project


The electrical contractor pays the subcontractors a fixed fee plus mileage for work performed. On the given day contractor is faced with 3 electrical jobs related with different projects. Every subcontractor will have adequate time to work on up to 2 projects during day. Every project must be completed by exactly 2 subcontractors. Given below are distances between subcontractors and projects

i) Sketch the network to represent possible subcontractor-project assignments.

ii) Create the linear model that would be used to minimize total mileage costs.

Projects

Subcontractor

A

B

C

Westside

2

3

4

Federated

6

1

5

Goliath

5

6

6

Universal

11

2

3