Single station with production rate


Consider the production system which consists of single station with the production rate of one part per minute and process variability given by Ce=1.

a) Suppose the system is run as the push line with release rate of .9 parts per minute and Ca=1. Employ the VUT equation to calculate the average cycle time and average number of parts in system. Then evaluate what occurs to the average cycle time and number of parts in system when process variability is eliminated so that Ce=0

b) Now assume the system is run as a CONWIP line with the WIP level of one job and has original variability levels Ce=Ca=1. What is average throughput rate and cycle time? What takes place to throughput and cycle time when we eliminate process variability of the Ce=0?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Single station with production rate
Reference No:- TGS014527

Expected delivery within 24 Hours