Show the equivalent units for materials and conversion


Because most of the parts for its irrigation systems are standard, Waterways handles the majority of its manufacturing as a process cost system. There are multiple process departments. Three of these departments are the Molding, Cutting, and Welding departments. All items eventually end up in the Package department which prepares items for sale in kits or individually.

The following information is available for the Molding department for January.

Work in process beginning:

Units in process ....................$22,000
Stage of completion for materials .............80%
Stage of completion for labor and overhead ........30%
Costs in work in process inventory:
Materials ........................$168,360
Labor ........................$67,564
Overhead .......................$17,270
Total costs in beginning work in process ..........$253,194
Units started into production in January ...........$60,000
Units completed and transferred in January .........$58,000

Costs added to production:

Materials ......................$264,940
Labor ........................$289,468
Overhead .......................$60,578
Total costs added into production in January .........$614,986
Work in process ending:
Units in process ....................$24,000
Stage of completion for materials .............50%
Stage of completion for labor and overhead .........10%

Instructions:

(a) Prepare a production cost report for Waterways using the weighted-average method.

(b) Show the equivalent units for materials and conversion costs if Waterways used FIFO instead of weighted-average.

Solution Preview :

Prepared by a verified Expert
Corporate Finance: Show the equivalent units for materials and conversion
Reference No:- TGS01258394

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)