Show the bill of material product structure


Utilizing the Step-by-Step MRP Calculation Process, students will solve the following MRP problem given: Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. Product C is made of two units of F and two of E. Product A has a lead-time of one week. Products B, C and E have lead-times of two weeks. Products D and F have a lead-time of three weeks.

a. Show the bill of material (product structure tree).

b. If 100 units of A are required in week 10, develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.

Grading Criteria:

  1. Student will demonstrate their relevant knowledge of MRP

  2. Apply critical thinking in applying MRP concepts

  3. Create an Master Production Schedule and a Material Requirement Planning Chart

  4. If there is a positive net requirement in a week, backward schedule by the lead-time and enter the quantity for the planned order release that will satisfy the net requirement.

 

 

Solution Preview :

Prepared by a verified Expert
Strategic Management: Show the bill of material product structure
Reference No:- TGS0905524

Now Priced at $40 (50% Discount)

Recommended (92%)

Rated (4.4/5)