Shirley Hopkins is developing a problem in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activities Immediate Predeccesor(s) Time (days)
A -- 2
B -- 5
C -- 1
D B 10
E A,D 3
F C 6
G E,F 8

a) Develop an AON network for this problem.
b) What is the critical path?
c)What is the total project completion time?
d)What is the slack time for each individual activities?

 