shirley hopkins is developing a problem in


Shirley Hopkins is developing a problem in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activities Immediate Predeccesor(s) Time (days)

A -- 2
B -- 5
C -- 1
D B 10
E A,D 3
F C 6
G E,F 8

a) Develop an AON network for this problem.

b) What is the critical path?

c)What is the total project completion time?

d)What is the slack time for each individual activities?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: shirley hopkins is developing a problem in
Reference No:- TGS0393495

Expected delivery within 24 Hours