Shawns shoes is trying to improve their operations by


1. Shawn's Shoes is trying to improve their operations by optimizing the number of machines.

2. The longest task takes 1.5 minutes to complete, and the total time for all tasks is 8.6 minutes. This product line operates 480 minutes per day.

3. How many machines are needed if Shawn wants 780 shoes to be produced each day?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Shawns shoes is trying to improve their operations by
Reference No:- TGS02492223

Expected delivery within 24 Hours