Assignment Task: Horizontal and Vertical Curves

Setting out the centre line of a roadon an embankment

Calculation of the centerline co-ordinates (Easting, Northing and Reduced Level) from the given design parameters.

The centerline co-ordinates are to be set out at multiples of 10 meters of chainage, starting at Point A, Chainage 0.000m, including the tangent points, and continuing to Point B, Chainage 250.000m.The road will eventually continue, in a straight line, towards Point C. Point C does not need to be set out; however, its co-ordinates are to be used to enable you to undertake the calculations.

The design parameters are as follows: -

Point                     mE                   mN                  Chainage       

A                            ?                      ?                       0.000m

TP1                    834.962          2900.218                 18.000m

IP1                      892.000          2929.400                N/A

TP2                         ?                        ?                        ?

TP3                         ?                        ?                        ?

IP2                      1001.500         2909.750                 N/A

TP4                          ?                        ?                       ?

B                              ?                        ?                  250.000m

C                          1080.000         2968.250                ?

The radius for first curve is to be 190m; the radius for second curve is to be 100.000m.

The road has a rising gradient of 3%, starting at ch0.000m and a falling gradient of 2.5% starting at ch 130.000m. The vertical curve begins at ch60.000m and has a total length of 120.000m.

Designed Road Level at ch0.000m is to be 92.900m.

Crossfalls are as follows:

ch. 0.000m to ch.18m 0%

ch. 70.000m +2%

ch. 140.000m to ch.150.000m 0%

ch. 190.000m -2%

ch. 230.000m 0%

The rate of change of crossfall is to be proportional to the change in chainage.

A plus value for the crossfall indicates that, looking along the direction of increasing chainage, the left hand side of the road will be the higher.

The Horizontal and Vertical Curves Assignment Help service offered by the professional tutors of Tutorsglobe is always by your side to precisely deal with your complex and tricky assignments and homework with ease.

Tags: Horizontal and Vertical Curves Assignment Help, Horizontal and Vertical Curves Homework Help, Horizontal and Vertical Curves Coursework, Horizontal and Vertical Curves Solved Assignments

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Setting out the centre line of a roadon an embankment
Reference No:- TGS03042119

Expected delivery within 24 Hours