Set a start date of september 1 2018 assume that work can


Create a Gantt Chart for the following project, and show the Gantt Chart below. 

Set a start date of September 1, 2018.  Assume that work can be done 5 days per week, with no work done on Saturdays or Sundays. 

Identify the Critical Path.  When will the project be completed?

Task Number

Activity

Immediate Precedence

Task Duration (Days)

1.

Strategic Planning Phase

none

20

2.

Team Orientation

1

28

3.

Software Configuration

2

60

4.

Testing

3

20

5.

Training

2

10

6.

Facility Modification

1

45