sequence the jobs shown below by using the gantt


Sequence the jobs shown below by using the Gantt chart. Assume that the move time between machines in one hour. Sequence the jobs in priority order 1,2,3,4. Job Work Center/Machine Hours Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 What is the makespan and machine idle time?