Sequence jobs according to spt find the average cycle time


Job                Processing Time in Days                   Due Date (Day)

1                                     7                                              8

2                                     1                                             12

3                                     5                                              6

4                                     2                                              4

5                                     6                                             18

Using the data in the table above:

a) Sequence jobs according to SPT

b) Find the average cycle time for using the sequence you found in part a

c) Find the total tardiness for using the sequence you found in part a

d) Find the maximum lateness for using the sequence you found in part a

e) Find the makespan for using the sequence you found in part a

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Sequence jobs according to spt find the average cycle time
Reference No:- TGS02584746

Expected delivery within 24 Hours