Seasons estimates total costs


Reasons Construction is constructing an office building under contract for Cannon Cafe. The contract calls for progress billings and payments of $620,000 each quarter. The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010.

Seasons Construction completes the remaining 25% of the building construction on December 31, 2012, as scheduled. At that time the total costs of construction are $7,500,000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2012?