Safety inventory of coal and mro materials is kept at twice


Question: what are your rates for answering?

A power plant in California uses coal at the rate of 80,000 pounds each day. It also uses MRO material at the rate of 800 pounds each day. The coal comes from Wyoming and the MRO material comes from Chicago. Coal costs $0.02 per pound, whereas MRO material costs $10 per pound, on average. Holding costs at the power plant are 25 percent. Transportation choices available are as follows:

Train:

Lead time = 15 days

Carload (100,000 pounds) at $400 per carload

Full train (50 cars) at $15,000 per train

Truck:

Lead time = 4 days

Between 10,000 and 25,000 pounds at $0.07 per pound for entire load

Between 25,000 and 40,000 pounds at $0.06 per pound for entire load

Small TL (40,000 pounds) for $2,000

Safety inventory of coal and MRO materials is kept at twice the consumption during the lead time of supply.

What mode of transport do you recommend for each of the two products?

Solution Preview :

Prepared by a verified Expert
Operation Management: Safety inventory of coal and mro materials is kept at twice
Reference No:- TGS0950833

Now Priced at $12 (50% Discount)

Recommended (91%)