risk determinationfor purpose of relative risk


Risk Determination

For purpose of relative risk assessment, risk equals probability of vulnerability occurrence TIMES value MINUS percentage risk already controlled PLUS an element of uncertainty. For instance

• Information asset A has a value score 50 and has 1 vulnerability: Vulnerability
1 has a likelihood of 1.0 with no current controls and you estimate that the assumptions and data are 90 percent accurate.
• Information asset B has a value score of 100 and has 2 vulnerability 2 has a likelihood of 0.5 with a current control which addresses 50 percent of risk. Vulnerability
3 has a likelihood of 0.1 with no current controls.

Resulting ranked list of risk ratings for the 3 vulnerabilities:

 Asset A: Vulnerability 1 rated as 55 = (50 x 1.0) –0% + 10% Where 55 = (50 x 1.0) – ( ( 50x 1.0)x0.0) + ( ( 50x1.0) x 0.1)
55 = 50 - 0 + 5

Asset B: Vulnerability 2 rated as 35 = (100 x 0.5) – 50% + 20% Where 35 = (100 x 0.5) – ( (100 x 0.5)x 0.5) + ( ( 100 x0.5) x 0.2)
35 = 50 – 25 + 10

Asset C: Vulnerability 3 rated as 12 = (100 x 0.1) – 0% + 20% Where 12= (100 x 0.1) – ((100 x 0.1) x 0.0) + ((100 x0.1) x 0.2)
12 = 10 - 0 + 2