A product requires four steps to complete.

Step 1 takes 8 minutes

Step 2 takes 6 minutes

Step 3 takes 2 minutes

Step 4 takes 10 minutes

20% of all units produced requires rework. For reworking, they have to revisit steps 3 and 4. Each step is processed by one employee. Rework takes the same processing times as the first pass and always fixes the problem. What is the capacity of the process in units per minute?