QUESTION - ABC & Associates is a public accounting firm that specialises in providing accounting and auditing service. Its job-costing system has one direct cost pool, professional labour and a single indirect cost pool that includes all supporting costs of running the office. The support costs are allocated to clients on the basis of professional labour-hours. In addition to the two senior partners, ABC has six partners who work directly with clients. Each of the eight partners is expected to work for approximately 2 650 hours a year. Budgeted and actual costs for 2016 were:

Budgeted professional labour costs

$4,240,000

Budgeted support costs

$2,000,000

Actual professional labour costs

$4,893,000

Actual support costs

$2,400,000

Actual total professional hours

23,300 hours

Required: Calculate the indirect costs rate per professional labour-hour under:

(a) Actual costing

(b) Normal costing

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Required calculate the indirect costs rate per professional
Reference No:- TGS02515974

Now Priced at $30 (50% Discount)

Recommended (92%)

Rated (4.4/5)