Recognizing revenue according to percentage of completion


Long-term contract; revenue recognition over time; profit recognition]

Response to the following problem:

A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract?

 