Recognizing a direct material price variance


If a company follows a practice of isolating variances at the earliest point in time, what would be the appropriate time to isolate and recognize a direct material price variance?

a. When material is issued.

b. When material is purchased.

c. When material is used in production.

d. When production is completed.