questionpart aborrico ltd manufacture a single


Question

PART A

Borrico ltd manufacture a single product and they had currently introduced a system of budgeting and variance analysis.

The subsequent information is available for the month of July 2011:

1.

 

Budget

 

Rs

Actual

 

Rs

 

Direct materials

200,000

201,285

 

Direct labour

313,625

337,500

 

Variable manufacturing overhead

141,400

143,000

 

Variable sales overhead

64,400

69,500

 

Fixed manufacturing overhead

75,000

71,000

 

Administration costs

150,000

148,650

2. Standard costs were:

Direct labour 48,250 hours at $6.50 per hour

Direct materials 20,000 kg at $10 per kg

3. Actual manufacturing costs were:

Direct labour 50,000 hours at $6.75 per hour. Direct materials 18,900 kg at $10.65 per kg

4. Budgeted sales were 20,000 units at $50 a unit.

Actual sales were:

15,000 units at $52 a unit

5,200 units at $56 a unit

5. There was no work in progress or inventory of finished goods

Required:

(a) Determine the direct materials cost variance, direct materials usage variance and direct materials price variance.

(b) Evaluate the direct labour cost variance, direct labour efficiency variance and direct labour rate variance.

(c) What  use  can  the  management  of  Borrico  Ltd  make  of  the  variances calculated in (a) and (b) above.

PART B

XYZ company manufacture and market a specific product which they sell at $20 per unit. Current production is 400,000 units per month which represents 80% of capacity. They have the opportunity to utilize their surplus capacity by selling their product at Rs 13 per unit to an outside buyer.

Total costs for the last month were $5,600,000 of which $1,600,000 were fixed cost. This represented a total cost of $14 per unit.

Required:

Based on the provided financial information only, should XYZ company accept the order?

PART C

Describe the opportunity cost concept and why it is used in decision making.

Request for Solution File

Ask an Expert for Answer!!
Cost Accounting: questionpart aborrico ltd manufacture a single
Reference No:- TGS0358284

Expected delivery within 24 Hours