question1 create 15 or more decomposed work


Question

1. Create 15 or more decomposed work packages into 4 levels that are assigned to 5 or extra main tasks (75 line items).

2. Ensure the answer WBS tasks headings are the 5 PMBOK® process areas (Initiating, Planning, Executing, Monitoring& Controlling and Closing)

3.generate a Work Breakdown Structure Code for each task.

4. Establish an overall project duration and duration estimates for each of tasks. The duration period is not to go beyond 90 days.

5. Produce accurate work package assumptions and duration estimates.

6. Include 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.

7. Ensure the Resources are paid no more than $30 per hour and that the "Material" cost per use will not exceed $50.

8. Include your resources and materials from the Resource Sheet in the task sheet.

9. make 10 dependencies in the Task Sheet

 

Request for Solution File

Ask an Expert for Answer!!
Computer Engineering: question1 create 15 or more decomposed work
Reference No:- TGS0444470

Expected delivery within 24 Hours